Question 1

If the total part failure rate of a machine is 0.00055 failures per hour, what would be the mean time between failures (MTBF) in hours? 


Answer: A
Question 2

When the discrete available-to-promise (ATP) method is used, the master production receipt quantity is committed to: 


Answer: C
Question 3

Which of the following systems would be the most cost-efficient for inventory management of a low value item? 


Answer: C
Question 4

One way to mitigate liability risk in the supply chain is to: 


Answer: B
Question 5

Which of the following capacity planning methods uses the master production schedule (MPS) as its primary input?


Answer: B
Page:    1 / 31   
Total 152 questions | Updated On: Sep 03, 2026

Quickly grab our CPIM-8.0 product now and kickstart your exam preparation today!

Name: Certified in Planning and Inventory Management (CPIM 8.0)
Exam Code: CPIM-8.0
Certification: Certified Production and Inventory Management
Vendor: APICS
Total Questions: 152
Last Updated: Sep 03, 2026