Question 1

What phase of the integrative process gives the team the greatest chance of success in meeting the project's environmental goals cost-effectively? 


Answer: B
Question 2

A project team member has prepared a map and accompanying table as documentation for the Location and

Transportation Credit. Surrounding Density and Diverse Uses. Option 2. Diverse Uses. The map includes the

location of each diverse use. the location of the project and the main entrance of the building. The table

includes the distance to each use. the name of each use and the category of each use The team lead reviews

the documentation and notes an important missing item. Which of the following is the most important item to

add to the documentation?


Answer: C
Question 3

The WaterSense label or local equivalent requirement in Water Efficiency Prerequisite, Indoor Water Use Reduction ensures that eligible newly installed plumbing fixtures will 


Answer: B
Question 4

Sustainable Sites Credit, Site Assessment requires evaluation of 


Answer: C
Question 5

A project team compares a life-cycle assessment (LCA) model to a baseline design to determine the reductions in six impact categories. One impact category exceeds the baseline by 7%. Which alternative analyses should the team run to check different impact measurements?


Answer: B
Page:    1 / 62   
Total 307 questions | Updated On: Jan 04, 2026

Quickly grab our LEED-AP-BD+C product now and kickstart your exam preparation today!

Name: LEED AP Building Design + Construction (LEED AP BD+C)
Exam Code: LEED-AP-BD+C
Certification: LEED Professional Exams
Vendor: USGBC
Total Questions: 307
Last Updated: Jan 04, 2026