MSP MSP-Practitioner

Page:    1 / 29   
Total 142 questions | Updated On: Apr 23, 2024
Question 1

The programme is currently in Tranche 2. The COO has been appointed as the SRO and the IT Manager is the programme manager. Due to the SRO’s lack of IT knowledge, the programme manager has found that it is easier to omit reporting about the IT issues as it often worried the SRO, who then created friction with the Process Alignment Project team.
Is this an appropriate application of the 'decisions' theme, and why?


Answer: D
Question 2

The Culture Alignment Project took longer than expected, meaning the Sales Channel and Processes Project was also affected. This delayed the end of the tranche. Therefore, the Estates/Buildings Rationalization Project started late, which delayed the end of Tranche 3. The programme is now in the ‘close the programme’ process, and the programme team is reviewing the overall performance of the programme. The programme office is updating the programme documentation to reflect the final position.
Which theme is MOST relevant to this activity?


Answer: D
Question 3

The sales personnel from both PCSafe and TechStore have a lot of very important knowledge about the two different markets. This has been gathered over time but has never been formally documented. For the Merger Programme to be successful, it is vital that this knowledge is shared, so that the new PCTech organization is better at competing with its competitors.
Which is MOST LIKELY to encourage knowledge sharing?


Answer: B
Question 4

The BCM has suggested that the schedule to achieve the increased sales and reduced costs should be integrated with the programme's schedule for delivering the projects. This would create a single view of the programme's work to deliver the new sales processes and channels as well as the increased sales and reduced costs. The programme manager has opposed this, believing it to be an invalid interpretation of the ‘structure’ theme.
Is the programme manager correct, and why?


Answer: C
Question 5

A risk assessment identified that the costs associated with terminating employment in different regions around the world were unpredictable. These cost variations could have a major impact on the profitability of the merger. As a result, the PCTech directors decided to continue with the merger but agreed that contingency should be set up based on industry benchmark data.
Is this an appropriate application of the ‘justification’ theme, and why?


Answer: A
Page:    1 / 29   
Total 142 questions | Updated On: Apr 23, 2024

Quickly grab our MSP-Practitioner product now and kickstart your exam preparation today!

Name: MSP Practitioner Exam (5thEdition)
Exam Code: MSP-Practitioner
Certification: MSP Programme Management
Vendor: MSP
Total Questions: 142
Last Updated: Apr 23, 2024