Question 1

The project’s change control approach states that PRINCE2’s recommended issue and change control procedure will be used. The senior user has requested that a new set of marketing materials and marketing channels be introduced to support the launch of the training course. The senior user has suggested that this should be managed informally. Where should the project manager record the issue, and why?


Answer: B
Question 2

While preparing the Configuration Management Strategy, the Project Manager considered the options for change control. He decided to recommend a change budget of £250k, but was undecided on the Change Authority to recommend. Which option is an appropriate Change Authority for the Outsourcing project?


Answer: B
Question 3

ABC Company has set an overall budget for the Health and Safety Training Project. During stage 3, there was a delay in delivering the 'e-learning course' by the external consultancy and the cost and time tolerance for the work package was exceeded. This led to additional costs in running the 'planned pilot courses'. Therefore, the project cost will exceed the agreed overall project budget, so the project board requested additional funding from ABC Company’s board of directors. Is this an appropriate action, and why?


Answer: D
Question 4

Which 2 statements apply to either the Techniques, processes and procedures or Constraints sections? 


Answer: A,D
Question 5

The 'e-learning course' is being delivered by an external consultancy. The testing of the e-learning has been completed by ABC Company’s testers and some faults have been found that still need to be fixed. The team manager for the 'e-learning course' work package believes the faults can be fixed within existing work package tolerances and has raised a request for change with the project manager. Is this an appropriate action, and why?


Answer: C
Page:    1 / 75   
Total 375 questions | Updated On: Apr 22, 2024

Quickly grab our PRINCE2-Practitioner product now and kickstart your exam preparation today!

Name: PRINCE2 Practitioner
Exam Code: PRINCE2-Practitioner
Certification: PRINCE2
Vendor: PRINCE2
Total Questions: 375
Last Updated: Apr 22, 2024