Question 1
Test Management
Consider an agile team adopting Extreme Programming (XP) with five developers and one
tester without any coding experience.
To which of the following activities would you expect the tester will contribute most?
Number of correct responses: 1
K2 1 credit
Answer: D
Question 2
Test Management
Based on the historical data of 5 past and similar projects, you have calculated these
average numbers of defects detected in system testing:
- for each 10000 LOC (lines of code), 200 defects
- for each person-month of development team effort, 49 defects
You want to use this information to perform estimation for a new project.
The project manager tells you that he/she has estimated 20000 new LOC for this new
project.
Four developers work for four months on this project before system testing.
During system testing, 797 defects are discovered.
Assume that the system test of this new project is using the same amount of work as spent
in the past projects.
Based on this information only, which of the following statement is certainly true about this
project?
Number of correct responses: 1
K3 3 credits
Answer: B
Question 3
Defect Management
Assume you are working on a defect management process to be used by a software
organization to track the current status of the defects reports for several projects.
When a defect is found for investigation a defect report is created in “Opened” state that is
the unique initial state. The defect report status has also a unique finale state that is the
“Closed” state.
The following state transition diagram describes the states of this defect management
process:
where only the initial (“Opened”) and final (“Closed”) states are indicated while the
remaining states (V, W, X, Y, Z) have yet to be named.
Which of the following assignments would you expect to best complete the defect
management process?
Number of correct responses: 1
K3 2 credits
Answer: C
Question 4
Test Management
Which of the following statements, about the test reporting activities for a project adopting
an iterative lifecycle model with very short iterations (e.g. two weeks iterations), is correct?
Number of correct responses: 1
K2 1 credit
Answer: D
Question 5
Testing Process
Which of the following is an example of the test closure activity indicated as "lessons
learned"?
Number of correct responses: 1
K2 1 credit
Answer: C
Page: 1 / 13
Total 65 questions | Updated On: Apr 25, 2024
Quickly grab our CTAL-TM_Syll2012 product now and kickstart your exam preparation today!
Name:
ISTQB Certified Tester Advanced Level - Test Manager [Syllabus 2012]
Exam Code:
CTAL-TM_Syll2012
Certification:
iSQI
Vendor:
iSQI
Total Questions:
65
Last Updated:
Apr 25, 2024
Enable immediate unrestricted access to all CTAL-TM_Syll2012 materials
Unlock all CTAL-TM_Syll2012 features instantly for just $52 inclusive of all benefits.
Expert-Verified Q&A: Trustworthy questions and answers, vetted by subject matter experts.
Intuitive Exam Practice Interface: User-friendly platform designed for seamless practice sessions.
Realistic Practice Modes: Varied modes offering an experience close to actual exam conditions.
Convenient Web-Based Testing: Access practice tests directly through your web browser.
No Installation Needed: Enjoy hassle-free preparation without the need for third-party software.
Flexible Learning: Self-paced study with round-the-clock customer support for guidance.