iSQI CTAL-TM_Syll2012DACH

Page:    1 / 13   
Total 65 questions | Updated On: Apr 23, 2024
Question 1

Topic 4, Defect Management


Defect Management
Consider a defect report and assume that a part of its lifecycle includes the following
states:
New: Is the initial state
Working: Means that the developers are addressing the defect in order to produce a fix for
the defect
Clarification: Means that the developers need more information from the tester to address
the defect and produce a fix for the defect and the tester is working to provide this
information to the developers
Verification: Means that a fix for the defect has been produced and the tester is running the
adequate tests to verify whether the fix solves the defect
Closed: is the final state
Which of the following answers represents an invalid sequence of states that can’t lead the
bug report to the “Closed” state?
Number of correct responses: 1
K2 1 credit
 


Answer: C
Question 2

The following are the requirements identified as “critical”:
REQ-SEL-001. The user shall be able to combine all the three products with all the four
durations to define an item to purchase
REQ-SEL-002. The user shall be able to add a maximum of six different items to the
shopping cart
REQ-PUR-001. The user shall be able to purchase all the items in the shopping cart using
a credit voucher
REQ-PUR-002. The user shall be able to purchase all the items in the shopping cart using
the available credit already charged on the smartcard
REQ-PUR-003. The user shall be able to purchase all the items in the shopping cart using
all the accepted credit cards (Visa, MasterCard and Great Wall Card)
REG-LOGO-001. The user shall be able to logout (by clicking the logout button) from both
the “select” and “purchase” pages going back to the “browse” page (anonymous
navigation)
Moreover the following quality risk item has been identified as “critical”:
QR-P1. The web customer portal might not be able to provide the expected response time
(less than 10 sec) for the purchase transactions under a load of up-to 1000 concurrent
users
Test analysis for system testing has just begun and the following test conditions have been
identified:
TC-SEL-01. Test the combinations of products and durations to define an item to purchase
TC-SEL-02. Test the maximum number of items, which can be added to the shopping cart
TC-PUR-01. Test the purchase of an item
TC-PUR-02. Test the purchase of an item with the credit charged on the smartcard
What is the MINIMUM number of test conditions that must be added to fulfill both the
EXCR1 and EXCR2 exit criteria?
Number of correct responses: 1
K3 2 credits


Answer: C
Question 3

Test Management
In the next two months some new features will be constantly added to new releases of a
project you are working on as Test Manager.
You have identified as one of the main project risks, that the requirements specification will
still be incomplete when your team starts the test design and implementation phase.
Some requirements will most likely be completed too late to allow a proper test preparation.
You and your test team have already worked on several similar past projects in the same
organization.
Which one of the following options would you expect to be the most effective at mitigating
this risk?
Number of correct responses: 1
K4 3 credits


Answer: B
Question 4

Topic 2, Test Management


Test Management
Which of the following statements about management of product quality risks in mature
organizations with respect to the lifecycle, is true?
Number of correct responses: 1
K2 1 credit 


Answer: B
Question 5

Test Tools and Automation
In your organization the following tools of the same vendor are currently in use: a
requirements management tool, a test management tool and a bug tracking tool.
You are the Test Manager.
You are currently evaluating a test automation tool of the same vendor (to complete the
vendor's tool suite) against an interesting open-source test automation tool under the GNU
GPL (General Public License).
There are no initial costs associated to that open-source tool.
Which of the following statements associated to the selection of the open-source tool is
correct in this scenario?
Number of correct responses: 1
K2 1 credit


Answer: B
Page:    1 / 13   
Total 65 questions | Updated On: Apr 23, 2024

Quickly grab our CTAL-TM_Syll2012DACH product now and kickstart your exam preparation today!

Name: ISTQB Certified Tester Advanced Level - Test AnalystISTQB Certified Tester Advanced Level - Test Manager (Syllabus 2012, D, A, CH only)
Exam Code: CTAL-TM_Syll2012DACH
Certification: ISQI certification
Vendor: iSQI
Total Questions: 65
Last Updated: Apr 23, 2024