PMI PMI-RMP

Page:    1 / 89   
Total 445 questions | Updated On: Apr 23, 2024
Question 1

Your organization has named you the project manager of the JKN Project. This project has a BAC of $1,500,000 and it is expected to last 18 months. Management has agreed that if the schedule baseline has a variance of more than five percent then you will need to crash the project. What happens when the project manager crashes a project?


Answer: C
Question 2

You are the project manager of the HJH project for your company. In your project, you have created the probability-impact risk matrix as shown in the following figure:

PMI-RMP-page148-image9
If Risk D happens in this project, how much will be left in the contingency reserve? 


Answer: B
Question 3

Which of the following will ultimately determine risk thresholds?


Answer: B
Question 4

Sammy is the project manager for her organization. She would like to rate each risk based on its probability and affect on time, cost, and scope. Harry, a project team member, has never done this before and thinks Sammy is wrong to attempt this approach. Harry says that an accumulative risk score should be created, not three separate risk scores. Who is correct in this scenario?


Answer: C
Question 5

A stakeholder is asked to approve additional funding to implement a risk response plan. However, the stakeholder is unsure of the amount that could be approved without escalation. Where should the stakeholder look to determine the amount that can be approved?


Answer: B
Page:    1 / 89   
Total 445 questions | Updated On: Apr 23, 2024

Quickly grab our PMI-RMP product now and kickstart your exam preparation today!

Name: PMI Risk Management Professional
Exam Code: PMI-RMP
Certification: PMI Risk Management Professional
Vendor: PMI
Total Questions: 445
Last Updated: Apr 23, 2024