Question 1

Tom is the project manager of the GHQ Project for his organization and he is working on recovering the project schedule. As Tom examines his schedule, he is especially aware of project activities with hard logic. What is hard logic? 


Answer: D
Question 2

Mary is the project manager for her organization. She is working with the project team to define the project activities. She is concerned about some of the dependencies of the project work, which may affect the project schedule. Which one of the following is the best example of a project constraint that will likely affect the project's ability to finish by a given deadline?


Answer: C
Question 3

Nancy is the project manager of the JJJ Project. This project has recently been approved by the project customer as complete so Nancy must now finalize the administrative closure. Nancy needs to create the final project report to report the successes and failures in the project. Who should Nancy deliver this final project report to if she is participating in a projectized structure?


Answer: C
Question 4

Once the project's WBS has been created what process may happen next?  


Answer: B
Question 5

You are the project manager for your organization. Management has offered you a bonus if you can complete the project work two months earlier than what your schedule predicts. You can use a schedule compression technique, but management does not want to increase costs in the project. What approach would you recommend to condense the project duration? 


Answer: A
Page:    1 / 65   
Total 325 questions | Updated On: Apr 24, 2024

Quickly grab our PMI-SP product now and kickstart your exam preparation today!

Name: PMI Scheduling Professional
Exam Code: PMI-SP
Certification: PMI SP
Vendor: PMI
Total Questions: 325
Last Updated: Apr 24, 2024